ADU STACK

Every cost,
in plain view.

Your ADU price breaks into five parts. Some are fixed for the whole cohort; others depend on your property. You'll see every line before you sign anything.

Estimated total

749 sq ft home1,199 sq ft home
1. Design and coordination Fixed$12,000–$18,000$15,000–$22,000
2. City fees Depends on your site$7,000–$16,000$15,500–$41,500
3. Utilities and connection fees Depends on your site$10,000–$35,000$12,000–$40,000
4. Foundation Depends on your site$15,500–$26,500$23,500–$40,000
5. The home itself (vertical construction) Fixed$183,500–$254,500$294,000–$407,500
Estimated all-in range$228,000–$350,000$360,000–$551,000

Planning ranges as of October 2026, not quotes. Your cohort proposal turns the fixed parts into firm numbers, and your site review narrows the rest.

Fixed Same for every home in the cohort Depends on your site Shown as a range until your site review
  1. 1Design and coordinationFixed

    One flat ADUStack fee from first site visit to move-in.

    749 sq ft home1,199 sq ft home
    Plan adaptation to your lot and finish choices$5,000–$7,000$6,000–$8,500
    Structural engineering and Title 24 energy report$3,000–$5,000$3,500–$6,000
    Permit coordination with your city$2,000–$3,000$2,500–$3,500
    Project coordination and materials sourcing$2,000–$3,000$3,000–$4,000
    Subtotal$12,000–$18,000$15,000–$22,000
  2. 2City feesDepends on your site

    Paid to your city and school district. The 749 sq ft plan avoids city impact fees entirely.

    749 sq ft home1,199 sq ft home
    Building permit and plan check$3,000–$12,000$4,000–$15,000
    School district fees¹$4,000$6,500
    City impact fees²$0$5,000–$20,000
    Subtotal$7,000–$16,000$15,500–$41,500

    ¹ Most districts charge up to $5.38 per square foot of home size (the 2026 state cap) on ADUs over 500 sq ft. ² California bars impact fees on ADUs of 750 sq ft or less. Above that, cities may charge fees scaled to the ADU’s size.

  3. 3Utilities and connection feesDepends on your site

    Getting water, sewer, and power from your main home to the ADU. Distance from the house and your existing electrical service drive most of this.

    749 sq ft home1,199 sq ft home
    Water and sewer lines (trenching and pipe)$6,000–$15,000$7,000–$16,000
    Electrical feed and subpanel$4,000–$8,000$5,000–$9,000
    PG&E service upgrade (only if your home has under 200 amps)$0–$8,000$0–$10,000
    Water and sewer connection or capacity fees (only if a separate meter is required)$0–$4,000$0–$5,000
    Subtotal$10,000–$35,000$12,000–$40,000
  4. 4FoundationDepends on your site

    Slab-on-grade, the simplest and most cost-effective foundation for a single-story ADU on a flat lot. Soil conditions, slope, and equipment access can change it.

    749 sq ft home1,199 sq ft home
    Soils report and foundation engineering$2,000–$4,000$2,000–$4,000
    Slab: excavation, forms, rebar, concrete$18–$30 per sq ft$13,500–$22,500$21,500–$36,000
    Subtotal$15,500–$26,500$23,500–$40,000
  5. 5The home itself (vertical construction)Fixed

    Everything from the top of the foundation up. Fixed per plan once your cohort’s contractor bid is in.

    749 sq ft home1,199 sq ft home
    Core materialsWhat’s inside the walls once it’s finished: framing or prefab structure, sheathing, roof structure and underlayment, insulation, rough plumbing and wiring, heating and cooling equipment and ducts, drywall.$70–$95 per sq ft$52,500–$71,000$84,000–$114,000
    Finish materialsWhat you see and touch: windows and doors, siding and roofing, flooring, cabinets and countertops, tile, plumbing fixtures, lighting, appliances, paint.$55–$85 per sq ft$41,000–$63,500$66,000–$102,000
    LaborThe crew that builds it: framing and assembly, plumbing, electrical and HVAC trades, drywall, finish carpentry, flooring, painting, cleanup, and on-site supervision.$120–$160 per sq ft$90,000–$120,000$144,000–$192,000
    Subtotal$183,500–$254,500$294,000–$407,500

What you'll see before you sign

  • Fixed design and coordination fee
  • Fixed price for the home itself, from your cohort's contractor bid, split into core materials, finish materials, and labor
  • The materials ADUStack supplies and their pricing
  • Your city's actual fees
  • Utility and foundation numbers from your own site review
  • Warranty terms, including 10-year structural coverage